- At Chequessett Neck Road, bridge construction continues with the past few weeks focused on installation of tapered pipe piles, rebar, and concrete, to comprise the footing for bridge pier 2. Excavation and stone armor installation continues.
- As planned, clean up for a staging area at Pole Dike Road (town pit) is complete and ready for use.
- Ongoing patience from residents and visitors regarding construction activity is appreciated.The project team continues to assess data and designs for next project elements. photos: Wes Stinson, Environmental Partners