Restoration Project Updates
Questions about the Herring River Restoration Project? Email: herringriver@envpartners.com or Call: (617) 657 – 0295
CNR Bridge Construction Continues – Pier 2
At Chequessett Neck Road, bridge construction continues with the past few weeks focused on installation of tapered pipe piles, rebar, and concrete, to comprise the footing for bridge pier 2. Excavation and stone armor installation continues. As planned, clean up for a...
Construction Begins on Permanent Chequessett Neck Road Bridge
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE MIG has begun work on the permanent bridge, beginning with the installation of steel sheeting around the perimeter of their current work zone. MIG's upcoming work will focus on installation of stone armor scour protection...
Temporary Bridge is Open on Chequessett Neck Road!
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE Following a brief pause, the installation of utility poles, conduits, manholes, and safety features were the final steps before Eversource and Verizon transferred power and telecom utilities across the temporary bridge. On...
Chequessett Neck Road Bridge Construction Update – February 2024
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE Following a brief pause, as the contractor awaited installation of two new Verizon utility poles, MIG construction will resume work the week of February 19th installing utility conduits and manholes in the existing layout of...
Herring River Restoration Project: Low Lying Roads – Construction Update
HERRING RIVER RESTORATION PROJECT: LOW LYING ROADS - CONSTRUCTION UPDATE New England Boring Contractors will be conducting geotechnical boring work at five locations along the low-lying roads stretching from Pole Dike Road and Bound Brook Island Road in Wellfleet...
Chequessett Neck Road Bridge Construction Update – December 2023
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE MIG Construction has completed installation of the temporary bridge piers and spans. The temporary roadway has been paved and the temporary storm water system is fully installed. Upcoming work will include: Installation of...
NEW Herring River Restoration Project Videos Now Online!
Friends of Herring River is pleased to present the first 2 videos – Herring Run and What’s Up with Duck Harbor? - within the current collection of the Herring River Restoration Project videos, produced by Solano Film Collective with funds from Massachusetts Division...
Cape Cod National Seashore Announces Funding Support and Contract Award for Major Herring River Restoration Project Component
Cape Cod National Seashore has awarded a contract for construction of the Mill Creek Water Control Structure (WCS), a crucial infrastructure component of the larger Herring River Restoration Project. The Mill Creek WCS will span the mouth of Mill Creek where it meets...
Chequessett Neck Road Bridge Construction Update – November 2023
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE MIG Construction continues to work on installation of the temporary bridge components. MIG has completed installation of the bridge piers that will carry the temporary bridge across the river. Upcoming work will include:...
Updates: Mill Creek Water Control Structure, Low Road Elevation & Culvert Replacement, Vegetation Clearing
Carole Ridley, Project Coordinator, Herring River Restoration Project Progress continues in the implementation of Phase 1 of the Herring River Restoration Project. Funding and environmental permits are in place for construction of all water control infrastructure and...
Chequessett Neck Road Bridge Construction Update – September 2023
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE MIG Construction is continuing to work on the Chequessett Neck Road bridge. Activities have focused on the installation of components that will comprise the temporary (by-pass) bridge. MIG has begun driving steel pipe piles...
Chequessett Neck Road Bridge Construction Update – August 2023
CHEQUESSETT NECK BRIDGE CONSTRUCTION UPDATE • MIG Construction has continued construction activities on the Chequessett Neck Road Bridge. Activities have focused on installation of components that will comprise the temporary bridge.• MIG has installed the steel...
Friends of Herring River
1580 Route 6, #5
Wellfleet, MA 02667
(508) 214-0656
info@herringriver.org
SUPPORT US
FOLLOW US